Contract Management · October 2026
By Remir Mukumov — APMG-accredited CP3P trainer, 25+ years in PPP advisory · Reviewed by the author · ~4 min read
Availability payments in PPPs are usually indexed once a year. A wrong indexation formula is barely visible in year one and very expensive by year fifteen.
The annual payment pays for two different things:
Only the first part should be indexed. Index the whole payment and the state compensates inflation on costs that are not rising.
Illustrative project: $10 million a year for 25 years. Operations 40%, capital and debt 60%. Inflation 6% a year.
Operating share indexed only:
Whole payment indexed:
That is $179 million in nominal terms, about $82 million in today's money at 4.5%.
Even with the right formula, overpayment happens in practice:
Inflation risk on operations reasonably sits with the state. Nothing in the contract requires it to pay more than that.
Illustrative calculation; real project parameters will differ.
Facing a similar issue on your project? Let us look at the numbers together.
Get Expert AdviceThis material is for educational purposes and does not constitute legal, investment or other professional advice.