Back in the 1990s, when I was deputy mayor for housing and utilities, I had an argument with the deputy mayor for finance and the heads of public institutions. It was about two numbers: how much was in the budget, and how much was needed to keep buildings warm.
The finance side insisted that schools and hospitals should take exactly as much heat as the budget allowed. I argued that we had to pay in full, otherwise classrooms would be cold and children would sit at their desks in padded jackets.
The second number is almost always higher than the first.
A road agency needs, say, 100 units a year to maintain its network, and the budget has 60. On paper everything looks fine, but every year 40 units of under-maintenance pile up. A couple of years later this turns into a spike in major repairs and a sharp drop in quality.
Until you calculate unconstrained O&M, you do not know the real price of the service. Without it, any PPP contract becomes a game of who blinks first.
First published in Russian in the Telegram channel «Просто о ГЧП» on 12 January 2026.
Facing a similar issue on your project? Let us look at the numbers together.
Get Expert AdviceThis material is for educational purposes and does not constitute legal, investment or other professional advice.